[sap-solution-manager] Charm Normal Correction Status Not Changing After Successful Test

Question from sonalkumar99 on Dec 30 at 5:06 PM
Hi team,

I am facing a problem in the normal correction steps, where I am not able to
proceed further to production after step"successfully Tested" in change
document.

Later it just gives me the option "release transport request". The
Maintenance cycle is in "Development with release" phase, but even if move to
other phases it doesn't affect. I have given the action log below. Please
suggest.

*General Note 20039431 2011/12/30 21:20:13*
*
*
*The status was set to the value E0011*
*
*
*General Note 20039431 2011/12/30 21:20:40*
*Requests DSMK900260 created*
*
*
*Action Create Transport Request in system DSM 910 of type Source Systems*
*completed*
*
*
*General Note 20039431 2011/12/30 21:22:07*
*The status was set to the value 'In Development'*
*
*
*General Note 20039431 2011/12/30 21:22:33*
*The status was set to the value E0012*
*
*
*General Note 20039431 2011/12/30 21:22:45*
*The status was set to the value 'Testing'*
*
*
*General Note 20039431 2011/12/30 21:23:30*
*The status was set to the value 'Successfully Tested'*

--
Regards,
sonalkumar nc
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2011 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
sonalkumar99  
 
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

No comments:

Post a Comment