Reply from BLGSRI on Apr 16 at 1:23 AM Hi Simon, Could you use activity elements where you would be able to enter different activity elements for labour hours and machine hours separately?
| | | ---------------Original Message--------------- From: Simon Walter Sent: Monday, April 16, 2012 1:12 AM Subject: Machine Hour and Labour Hour in Single Activity Hi Experts In my project, For completion of one internal activity it requires certain manpower hours and labour hours. The cost is driven through Activity Type, which i assign it in my work centre-which further assigned it in the Activity. I can only assign one activity type in my Network Activity, which could be either for manpower or machine. How do i calculate both the variable together for completion of one activity. Is PRT a solution, as i haven't worked on the same. Your Vital inputs required Thanks and Regards Simon | | Reply to this email to post your response. __.____._ | _.____.__ |