Reply from Lion1001 on Dec 30 at 7:40 PM thank you LUIGI...
| | | ---------------Original Message--------------- From: Lion1001 Sent: Friday, December 30, 2011 2:47 PM Subject: Actual Posting On WBS ELEMENTS Hi there, I have one situation at project system. Currently my clients want to move their project budget from SIGIP system. They wanted to bring all projects and Wbs element in SAP. They have budget on XYZ wbs element is about 250,000 USD. And they have spend 200,000. So I want to post 200,000 as actual. So they can have available balance of 50,000 USD. Please let me know what I can do for that. Thanks in advance. | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |