Question from prausantis on Jun 22 at 5:51 PM Hi everyone, I have an issue with project budgeting. I already plan cost for my project, total plan cost 235.606 usd in 2012. Then in CJ30, I copy the plan cost for the budget (100% plan cost). First, I copy 2012 and later overall the accumulative. The problem that I am facing is that budget value is not the same as plan cost. Plan cost 235.606 usd Budget 223.661 usd according S_ALR_87013558. The same report shows assigned value and Remordplan 235.606 usd and according to the report S_ALR_87013557 the budget value is 228.591 usd. I have the AVAC activated and it is automatic. The project doesn't have any commitments or actual. I haven't exclude any cost element from AVAC. The budget currency is the object currency which differs from the Controlling Area currency. At first, I thought that the problem was the exchange rate but I have two values in the budgeting so I don't know. Please help, Patricia | Reply to this email to post your response. __.____._ | _.____.__ |