Reply from TBN on Apr 23 at 2:58 AM Thanks for reply, My requirement is already purched stockeble material to some other new network because in the beginning of the project few network has been created and after some time when user create new network and want to goods issue this purchased material to new network.
| | | ---------------Original Message--------------- From: BLGSRI Sent: Monday, April 23, 2012 2:37 AM Subject: Issue Material to Some Other Network Activity Hi TBN, Do you want to issue the material ? or you are asking us whether can issue or not? If you want to issue the material to other network, you must do the stock transfer first using Mvt typ-311Q After that can issue | | Reply to this email to post your response. __.____._ | | TBN SAP PS Consultant | | _.____.__ |